The Tesla Semi finally has a public charging corridor outside California. Over the past few days, Tesla and truck-stop giant Pilot opened the first Megacharger at a Pilot travel center, Tesla opened its own site near Atlanta, and a Flying J in California's Central Valley came online. The openings matter because charging, not truck production, is now the main thing limiting how fast the Semi can spread.
What opened
- Ellabell, Georgia (Pilot #1390, 130 Interstate Exchange Way): six heavy-duty stalls, about 20 miles west of Savannah on I-16. Pilot announced it on Oct. 8 as the first site from the partnership it struck with Tesla in January.
- Conley, Georgia (1820 Rock Cut Road): eight Megachargers about 10 miles south of downtown Atlanta, per Tesla's location page as reported by Electrek. The Tesla Semi account posted on Oct. 8 that the Atlanta and Savannah sites were "now online," with "many more Southeast sites coming soon."
- Tulare, California (Flying J #1071, 979 E. Paige Ave.): Pilot listed an Oct. 9 opening date for this site.
Pilot says each stall can deliver up to 1.2 megawatts using Tesla's V4 cabinet hardware, which Tesla says restores about 60% of a Semi's charge in 30 minutes. Electrek notes the two Georgia sites sit roughly 220 miles apart, which lets a 325-mile Standard Range Semi run the Savannah port to Atlanta lane and back with one charge during the driver's break.
What's next
Pilot says 12 more heavy-duty charging locations are under construction. Two besides Tulare are near completion: a Flying J in Fort Stockton, Texas, and a Pilot in North Las Vegas, Nevada. Each site gets four to eight stalls. The target states are now California, Georgia, Indiana, Nevada and Texas; Electrek points out that January's list included New Mexico and not Indiana.
The investor angle: chargers are behind trucks
The rollout is late. When Pilot and Tesla announced the deal in January, the first sites were due this summer; the first one opened Oct. 8. Electrek counts about four customer-facing Megacharger sites and 26 stalls, against roughly 37 sites shown for 2026 in Tesla's Q4 2025 report and a stated goal of 46 by early 2027. Tulare would bring that count to five.
Meanwhile, Tesla started high-volume Semi production in late September at a Sparks, Nevada, plant it says can build 50,000 trucks a year, and Electrek reported it was named primary supplier for a 2,500-truck order from the ZET SCALE alliance. Fleets on fixed routes can install depot charging, but long-haul buyers need public stations along the corridor before they commit.
What to watch: how quickly Fort Stockton, North Las Vegas and the remaining Pilot sites open, and whether Tesla reports a Megacharger count or Semi deliveries in its Q3 earnings later this month. Tesla has not disclosed how many Semis it has delivered since volume production began.